Construction is completed on the Monroeville Solar Park (see our December 5, 2017 blog post), and commercial power production began December 28, 2017, the Norwalk Reflector reports. The 4-megawatt (MW) field “will offset about 10 percent of the village’s annual kilowatt hour (energy) purchases,” according to the article. Construction was completed ahead of schedule; weekly work by students and instructors from the EHOVE Career Center-Electrical Program “shaved time from the construction schedule with the end result [of] the project being commissioned at the end of 2017.” For more, read the full article.